Pakse International Airport Improvement Project to be completed on October 2009

(KPL) The Pakse International Airport Improvement Project which expanded the runway to 2,400 meter long and 45 meter wide to receive the landing and taking off of the aircraft of Boeing 737 and Airbus A 320, is now 18.5 per cent completed and is expected to be finished at the end of October this year.
Mr. Anoulack Khithilath, Head of the project said recently that the project signed a construction contract with Italian-Thai construction company on 1 March, 2008 with the cost of 233,999,999 bath (Thai currency) has to expand the runway from 1,650 m long to 2,400 m long and 36 m wide to 45 m wide. The runway will be paved with asphaltic concrete.
The five storey building air control station is being constructed.