ID :
691899
Sat, 11/16/2024 - 14:39
Auther :

Project for Installing UHP Electric Arc Furnace Propelled in DPRK

 Pyongyang, November 16 (KCNA) -- Officials and workers at the Chollima Steel Complex in the DPRK are stepping up at the final stage the construction of melting shop building for installing the 60-ton UHP electric arc furnace.
The workers of the repair station have assembled dozens of truss with a weight of more than 5 tons while strengthening inter-process cooperation.
Workers and technicians set up steel pillars, the main frame of the melting shop building, and are pushing ahead with the work to fill low ground with over 11 000 cubic meters of earth while increasing the operation rate of machines and equipment. -0-
 


X